Controlling Item / Descriptor Planned Costs when copying a Job

Controlling Item / Descriptor Planned Costs when copying a Job

This User Defined Constant modifies the behaviour when copying from one job to another. By default Ostendo will copy the originating job item and descriptor planned costs to the new job. (Labour Code planned costs are always refreshed with the current cost). 

There are some environments where they wish to always refresh these costs when a job is copied.

The following User Defined Constants allow you to control whether the costs are refreshed (for either or both Items and Descriptors) when the job is copied.


Constant Name: REFRESH ITEM COST ON JOB COPY

Type: Yes/No


Constant Name: REFRESH DESCRIPTOR COST ON JOB COPY

Type: Yes/No

    • Related Articles

    • How does Ostendo determine the Assembly receipt Costs and Variances?

      1. First look at File>System Configuration>System Settings and you will see that cost that is received into Stock. This is either Standard (which uses the Standard Cost held against the Received Parent Item) or Average (which uses the Actual Cost of ...
    • Use Assembly Planned Cost For Issue

      This constant allows you to control the Actual Issue Cost of a Descriptor on an Assembly Order. By default Ostendo issues descriptors using the Buy Price value. This constant allows you to issue the Descriptor at the Assembly Line Planned Cost ...
    • Setting up and maintaining Sell Prices for Item and/or Descriptors

      1. Inventory Items Basic Sell Price - To add the Base Sell Price go into Inventory>Items and add the base Sell Price. In the absence of any other Sell Price conditions this price will be used. If no Price is entered here then a zero Base Price is ...
    • How do I set up and maintain Sell Prices for Item and/or Descriptors?

      1. Inventory Items Basic Sell Price - To add the Base Sell Price go into Inventory>Items and add the base Sell Price. In the absence of any other Sell Price conditions this price will be used. If no Price is entered here then a zero Base Price is ...
    • How do I post a Deferred Income Job Invoice?